Location: 17900 Red Feather Lakes Road Red Feather Lakes, Colorado 80545
Owner: Girl Scouts-Mile Hi Council 400 South Broadway Denver, Colorado 80209Construction Manager:Pinecrest Planning & Design Mr. Tom Dugan 970-226-1655 4225 Westshore Way Fort Collins, CO 80525
Project & Design Engineer:Church OWC, LLC 9590 W. 14* Street Suite 100 Lakewood, CO 80215 720-898-3434 SRC Enterprises, Inc. P.O. Box 166 Pine, Colorado 80470 303-838-4446 | Operator: Alberts Water and Wastewater Fort Collins, Colorado
Engineer/Distributor:SCG Enterprises, Inc. Roger Shafer PE P.O. Box 1411 Conifer, CO 80433 303-697-9404
SRC Enterprises started the construction and installation of this system in the summer of 2006 with a start up date of January, 2007. The system was designed as a 20,000 GPD, effluent sewer and Advantex System. Summary of System:Installation Start Up Date: January, 2007Collection System: Small diameter effluent sewer with 13 Septic Tank effluent pumping (STEP) system connections.Treatment System: 1- 30,000 gallon Xerxes septic/anoxic tank 1-20,000 gallon Xerxes recirculation tank 1- 1,500 gallon precast concrete dosing tank 8-AX 100 AdvanTex Filters 2- Sanitron UV Disinfection Lights 1- Orenco TCOM telemetry system with Siemens Magnetic Flow Meters, Temperature probe, PH Probe, fan and heater control.
Dispersal System: Surface discharge to South Lone Pine Creek
|