Sewer Improvements:- Installation of a 15,000 Gallon Precast Concrete Tank
- Installation of Manhole Dosing Station With Pump.
- Installation of Manhole With 2-Inch Flow Meter
- Installation of Seven Leach Fields for 10,468 SF total of Drain Field Area.
- Installation of 3,500 lf of 3" Hope Sewer Service Line With Four Cleanout Manholes.
Water System Improvements:- Excavation, Compaction And Preparation of Tank Hole for 60,000 Gallon Cast-In-Place Potable Water Storage Tank.
- Installation of All New Water Main Transmission Lines And Service Lines.
- Removal And Discontinue Old Water Storage Tanks And System.
- Infiltration Gallery Well:
- Installation of 24.6' X 6' Precast Manhole for Gallery Well With Aluminum Bilco Hatch.
- Installation of Grundfos 1.5 Hp Pump on Gallery.
- Installation of 1,200 Lf of 2" Hope Water Service Line Installation of Stainless Steel Johnson Screen Inlet Line for Well Bedded in Clean Aggregates With PVC Liner in Trench